|
Design of Concrete Structures |
|
Engineering 5706 |
|
Laboratory Instructions for Reinforced Concrete Beams |
|
Laboratory Work |
|
In general, the laboratory report should be complete, concise, clear and presentable. The following items should form the base of the report: |
|
|
Justification for important decisions made along the way (main dimensions, materials, support conditions, etc.) should be discussed briefly. |
|
Problems encountered in conducting the experiment may also be discussed, along with any recommendations on how the test set-up and instrumentation might be improved. |
|
A single report on each experiment is to be submitted by each group. In addition to technical content, the organisation, clarity and neatness will be considered in assessing the report. In other words, the report should look as professional as possible. |
|
OBJECTIVES |
|
Among other things, the objectives include a study of the strength and behaviour of reinforced concrete beams. A beam will be tested under a concentrated load until failure. The cracking pattern and the failure characteristics will be observed. Finally, the nominal ultimate capacity of the beam will be recorded and compared to those obtained from theoretical calculations. |
|
REFERENCES |
|
CPCA Handbook, Class Notes, Text book by Pillai and Kirk. |
|
EQUIPMENT |
|
|
|
|
CASTING PROCEDURE |
|
The following procedure will be undertaken by each individual group: |
|
|
TESTING PROCEDURE |
|
The following procedure will be undertaken by each individual group: |
|
|
|
|
REPORT |
|
Among other things, the report, by each individual group, shall consist of the following: |
|
|
GIVEN DATA |
|
Basic Shapes of Beams: |
|
|
|
Loading arrangement: |
|
|
|
The reinforced concrete beam is to be deigned using to the following data: |
|
Dimensions: Each group will be given a beam dimension. The form-work for the beam is available at the concrete lab. The beam has either a Rectangular section or a T-section. |
|
Reinforcement: Grade 400 steel. Four sizes are used; #10, #15, #20 and #25 metric size. The top bars shall be #15 size. |
|
Concrete: the concrete will be delivered by a truck on the day of pouring. The nominal compressive strength of the concrete, f ¢ c, is 35 MPa. Actual strength will be as per cylinder tests. |
|
Beam: The beam will be cast for a length of 8 ft. The beam is simply supported with a span of 7.5 ft. The beam web is either 6" or 8". The overall depth is 12". For T-beams, the flange thickness will be 3" and flange projection from the face of web will be 4". The beam is in an interior and non-corrosive environment. Nevertheless, the concrete cover should be measured from the actual reinforcement cage and form-work of the beam before casting the concrete. Stirrups will be #10 size metric bars. Recommended spacing of stirrups is 100 mm (may be varied if necessary). |
|
RESULTS REQUIRED |
|
Complete analysis of the beam should be carried out. In doing the calculations, assume that the laboratory test load is the factored load (do not apply load factors). If using the actual measured material strengths, do not use the resistance factors. The following should be calculated: |
|
|
DEFORMATION CHARACTERISTICS |
|
Deflections |
|
The deflection at centre of the beam is measured using the internal LVDT of the hydraulic actuator. Additional dial gauges may be used as well. |
|
Steel Strains |
|
The steel strains can be measured in the centre of the span by means of electrical strain gauges. The steel electrical strain gauges are 10 mm long, 120 W resistance and a gauge factor of 2.04 ± .5 %. For protection against any possible water damage during casting, the strain gauges are coated with a sealant. |
|
Concrete Strains |
|
The concrete strains can be measured in the centre of the span by means of electrical strain gauges. The concrete electrical strain gauges are 50 mm long, 120 W resistance and a gauge factor of 2.07 ± .5 %. The strain gauges are glued on the concrete surface on a very thin layer of Epoxy bonding agent used to obtain an even surface. |
|
SUBMISSION |
|
Deadline line for submittal of the lab report is one week after the test. |
|
EVALUATION |
|
The evaluation of the lab work and report will be based on the following evaluation criteria |
|
1. |
Appearance of form-work and reinforcement cage |
5 % |
|
2. |
Concrete finish |
5 % |
|
3. |
Prediction of ultimate load |
10 % |
|
4. |
Complete analysis of the beam |
35 % |
|
5. |
Description and analysis of the results |
35 % |
|
6. |
Completeness and accuracy of final report |
10 % |
|
7. |
Negative marks will be applied for not meeting deadlines and improper work. |
|
|
Depending upon the performance, a short interview may be conducted to evaluate individual students in each group. |